Building Schedule
| Task | Complete |
| Site Clearing and Erosion Control | Jan 1 |
| Building Slab | Feb 1 |
| Walls and Roof | Feb 15 |
| Interior Framing | Mar 26 |
| Building Exterior | May 1 |
| Side Walks and Landscaping | May 1 |
| Building Interior | May 14 |
| Opening Ceremony | Jun 1 |
Note: All dates are approximate and subject to change.